Connecting high voltage premises
Learn about the conditions for making a high voltage (HV) connection. Learn how to request this connection from the 60kV network to the substation of the requester, the secondary electrical distribution network.
- You can connect to the high voltage network via overhead lines or underground cables;
- It is mandatory to have a high voltage cutting station (PCAT) near the substation of the customer with ancillary services for the PCAT remote control, fed by the medium voltage public distribution network;
- It must be possible to access the land destined for the cut-off point via the public road, so the surface use right will always be of EDP Distribuição, if it is not owned by teh company.
Consulte a rede de alta tensão e subestações
1. Aceda ao mapa;
2. Selecione a região onde ficará localizada a sua instalação;
3. Escolha a subestação;
4. Identifique a linha ou subestação onde prevê fazer a ligação;
5. Consulte as caraterísticas da rede, as pontas máximas e a carga da linha ou subestação.
Para formalizar o seu pedido de ligação à rede em AT deve contactar o seu gestor ou enviar um e-mail para plrat@edpdistribuicao.pt.
Preços médios de referência para uma ligação à rede de alta tensão de 60 kV
Para mais informações poderá contatar o gestor de cliente da EDP Distribuição através do endereço plrat@edpdistribuicao.pt.
- Conclusão das obras;
- Pagamento dos custos associados à ligação à rede elétrica;
- Licenciamentos e autorização de entrada em exploração pela Direção-Geral de Energia e Geologia;
- Assinatura do protocolo de exploração;
- Contrato de fornecimento com o comercializador de energia.
Para mais esclarecimentos ou informações poderá contactar o gestor de cliente da EDP Distribuição através do endereço plrat@edp.pt.