The professionals of the electric sector are the spokespersons of our activity.
In definitive premises, there are two segments to be made within low voltage connections:
Power exceeding 41,4kVA
We have defined the value of 41.4kVA as the required power from which a prior evaluation of the low voltage grid connection conditions will be required.
The evaluation of the total power requested corresponds to the sum of the powers of all the plants fed from the same branch, according to the concurrency coefficients provided for in the Technical Rules for Low Voltage Electrical Installation (RTIEBT), according to the electrical specifications.
If the building is new and has more than one extension, information must be provided on all planned feeds, so that we can assess the need to define special technical conditions for connections to the grid.
Check here the addresses where to send the documentation associated with your request of power grid connection exceeding 41.4kVA.
Powers less than or equal to 41,4kVA
We consider that requests for requested power less than 41,4kVA do not generally require prior assessment of connection conditions.
For these requests, the technical evaluation and definition of the respective charges will be made in the request of connection to the electric network.
Request a power grid here.
Sem prejuízo dos proprietários obterem essa informação, ou os técnicos responsáveis em nome deles, junto da EDP Distribuição, a DGEG disponibilizou diretamente através do site do SRIESP a consulta das potências máximas admissíveis e os tipos de entrada das instalações elétricas ligadas à EDP distribuição através da opção "Consulta do NIP", disponível no menu principal do SRIESP, após o devido registo do técnico responsável.”
Além do NIP, será também necessário o CPE da ou das instalações que pretende consultar. Poderá obter mais informação sobre este assunto poderá visitar o site do SRIESP.
Mais informamos que no caso dos restantes operadores de rede a DGEG ainda não disponibiliza esse serviço.